Cured-in-place pipe
Cured-in-place pipe: a new sewer line inside the old one
CIPP turns a leaking, root-bound pipe into a smooth, jointless one in a single day — through one access point, with the old pipe left in the ground as the form.
CIPP at a glance
Access
One cleanout or a single small access hole; no pits
Liner
Felt or glass-fiber tube, 4.5–6 mm thick on a residential lateral, cured with epoxy, vinyl ester or polyester resin
Cure time
Hot water 2–4 hr, steam 1–2 hr, UV a few feet per minute; one day on site
Diameter loss
About ¼–½ in. on a 4-in. line; flow usually improves
Standards and life
ASTM F1216 (inversion) and F1743 (pull-in); 50-year design life
Typical cost
$80–$250 per foot installed (cost page)
What a liner is
A cured-in-place liner starts as a soft sleeve — felt, fiberglass or both — cut to match the run's length and the host pipe's bore. Before installation it is saturated with a thermosetting resin — polyester, vinyl ester or epoxy, chosen for the service and the host pipe; epoxy is the usual choice on residential laterals because it shrinks the least. Once the resin cures the tube is no longer a tube; it is a rigid pipe, bonded closely to the inside of the old one, carrying its own structural load. The old pipe becomes a form that happens to be left in place.
On a 4- to 6-inch lateral the finished liner wall is typically 4.5 to 6 millimeters thick; mains get thicker liners sized by a design calculation that accounts for depth, groundwater and how much of the host pipe is left. That wall takes about a quarter to a half inch out of a 4-inch bore, and because the cured surface is far smoother than clay or scaled cast iron, the lined pipe usually carries as much flow as it did when new, or more.
Preparing the host pipe
The line is televised, measured and then cleaned with a hydro jetter at 3,000 to 4,000 psi until the camera shows bare pipe wall. Roots are cut back to the wall. Offset joints that would snag the liner are ground down with a robotic cutter. A protruding tap or a collapsed section that cannot be cleared means the line is not a lining candidate, which is exactly what the pre-inspection is for.
Installing it: inversion or pull-in
Two ways to get the liner into the pipe. In an inversion, air or water pressure everts the wet-out liner so that it unrolls down the pipe with its resin face against the wall; this is the method ASTM F1216 describes. In a pull-in, covered by ASTM F1743, the liner is drawn through the pipe by a winch and then inflated with a calibration bladder. Inversion is common for straight laterals and mains; pull-in suits short runs, bends and lines with limited access. Either way the liner is held against the host pipe under pressure through the whole cure.
Curing it
Resin cures with heat or light. Hot-water cure circulates through the inflated liner for about 2 to 4 hours on a lateral, followed by a controlled cool-down so the liner does not pull away from the host; steam cure does the same work in 1 to 2 hours. Ultraviolet cure draws a lamp train along a glass-fiber liner whose resin is light-initiated, advancing at a few feet per minute, and is the fastest option on mains. Ambient-cure epoxy systems, which harden on their own over several hours, are used for short laterals and under-slab work where heat is impractical. When the cure is complete the ends are trimmed flush and a camera-guided cutter reopens any branch lines from inside, a few minutes per connection.
What you end up with
A continuous pipe with no joints, no roots, and a wall smooth enough to improve flow despite the small loss in diameter. Properly designed liners are structurally independent of the host pipe and are designed for 50 years of service under ASTM F1216. Water is normally off for 4 to 8 hours on the day and back on the same evening. The post-installation video shows every foot of it.
Where CIPP is and is not the right method
Lining rebuilds damage; it does not correct geometry. Cracks, open joints, root intrusion, channeled cast iron and scale are lining jobs. A belly, a collapse, a flattened Orangeburg run or a line that has lost its slope needs pipe bursting or excavation. Drains beneath a slab that turn every few feet are often better suited to spray-applied lining. The method is decided by the camera, never by the proposal.
Common questions about CIPP
How long does CIPP sewer lining last?+
A structural cured-in-place liner is designed for a 50-year service life under ASTM F1216, the standard that governs the method, and liners installed in the 1970s are still in service. The liner is designed as a stand-alone pipe, so it does not depend on the old pipe for strength.
How much diameter do you lose with a CIPP liner?+
A residential liner is typically 4.5 to 6 millimeters thick, so a 4-inch pipe loses roughly a quarter to a half inch of diameter. Because the cured liner is far smoother than clay or scaled cast iron, flow capacity is usually equal or better despite the smaller bore.
How long does a CIPP liner take to cure?+
Hot-water cure on a residential lateral runs about 2 to 4 hours plus a controlled cool-down; steam cure 1 to 2 hours; ultraviolet cure moves along a glass-fiber liner at a few feet per minute; ambient-cure epoxy takes several hours and longer in cold ground. Installation plus cure is normally a single day.
Can a sewer pipe with bends be lined?+
Standard felt liners handle sweeps and bends up to about 45 degrees; 90-degree fittings, back-to-back bends and under-slab drains that turn every few feet are better suited to short pull-in liners or spray-applied epoxy lining.
What can't be fixed with pipe lining?+
A liner follows the shape of the host pipe, so it cannot fix a belly that traps water, a collapsed or flattened section, or a line that has lost its slope. Those need pipe bursting or excavation. A protruding tap or offset the cutter cannot grind flat also rules a line out until it is repaired.